Safe Harbor II Progress Update
The future is taking shape at Safe Harbor II! This week marked major progress as the construction crew continued advancing second and third floor framing while kicking off framing on the fourth floor. Plumbing rough-ins, fire sprinkler installation, and structural inspections are also moving forward, keeping the project on track for dry in before the rainy winter.
This week's key milestone was the installation of the site's rainwater catchment system, supporting Holos' long-term sustainability goals. With the building structure now prominently visible, we're excited to see this new development come to life.